Bogue Plant Retrofit to be Completed Soon
Retrofitting of the 120-megawatt Bogue Plant is scheduled to be completed in less than three months, enabling the use of liquefied natural gas (LNG) in Jamaica for the first time. According to the Electricity Sector Enterprise Team (ESET), the project is progressing on schedule and has a commercial operation date of August 15. Chair of ESET, Dr. Vincent Lawrence, speaking...