The Forum Bridge, located on the Port Henderson Road in Portmore, St. Catherine, is to be rehabilitated at a cost of $27 million.
Contract Signed for Rehabilitation of Forum Bridge
State Minister in the Ministry of Transport, Works and Housing, Hon. Richard Azan (3rd left), presents the signed contract for the rehabilitation of the Forum Bridge in Portmore, St. Catherine to General Manager for Quality Plus Contracting Company, Sheldon Goldbourne (2nd right). Occasion was the signing ceremony for the project held today (September 2), at the Jewels International Resort in Portmore. Others (from left) are: Permanent Sectary in the Ministry, Audrey Sewell; Manager for Communication and Customer Service at the NWA, Stephen Shaw; Member of Parliament for South East St. Catherine, Hon. Colin Fagan; Director of Major Projects at the NWA, O’Reilley Henry; and Acting Mayor of Portmore, Councillor Leon Thomas.

The Facts

  • Quality Henderson Plus Contracting Company will be undertaking the works, with the National Works Agency (NWA) as the implementing body.
  • The six-month project will include sand blasting, repair of bridge steel structure, repairs to steel girder, replacement of bridge bearing pads, scour protection works, and base and pavement reconstruction.

The Full Story

The Forum Bridge, located on the Port Henderson Road in Portmore, St. Catherine, is to be rehabilitated at a cost of $27 million.

The contract was signed today (Sept. 2) for the six-month project, which is expected to commence next week.

Quality Henderson Plus Contracting Company will be undertaking the works, with the National Works Agency (NWA) as the implementing body.

Addressing the signing ceremony held at Jewels Resort International in Portmore, State Minister for Transport, Works and Housing, Hon. Richard Azan, appealed for cooperation from residents during the construction phase.

He informed that traffic will be restricted to one way during peak hours and residents will be required to use a detour road.

“We are asking for cooperation and for the contractors to be able to complete the work on time,” he said.

The six-month project will include  sand blasting, repair of bridge steel structure, repairs to steel girder, replacement of bridge bearing pads, scour protection works, and base and pavement reconstruction.

Acting Mayor of Portmore, Councillor Leon Thomas, and Member of Parliament for South East St. Catherine, Hon. Colin Fagan welcomed the project.